No.
|
The total package units / construction unit
|
Project name
|
Construction Date
|
|
1
|
Zhengzhou Intercontinental Hotel (strong club Aberdeen)
|
Zhengzhou Intercontinental Hotel, dynamic lighting and installation of equipment
|
2000
|
|
2
|
China Petrochemical Group of 10 construction companies
|
Rizhao City, Shandong Province pulp and wood pulp factory workshop lighting and power distribution equipment installation works
|
2000 ~ 2002
|
|
3
|
China Petrochemical Group of the third construction company
|
Ningbo Port 25 tons of crude oil transit terminal electrical, instrumentation installation of automatic control
|
2002 ~ 2003
|
|
4
|
China Petrochemical Group of the third construction company
|
Ningbo City area Ningxing liquid chemical logistics terminal-controlled installation of the instrument
|
2002 ~ 2003
|
|
5
|
Zhengzhou University
|
New Campus of the University of Zhengzhou, Henan Province, two living rooms park level of distribution installation, commissioning works
|
2003
|
|
6
|
Zhengzhou University
|
New Campus of the University of Zhengzhou, Henan Province, the Integrated Management Center installation of air-conditioned room
|
2003
|
|
7
|
Zhengzhou, the Sadian
|
Zhengzhou Hotel Block A Pan-Lighting Project
|
2004
|
|
8
|
Zhengzhou Jincheng, a real estate company
|
Kim Sung-Zhengzhou International Trade Building, air-conditioning installation of the control line
|
2004
|
|
9
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Shenzhen Pinghu Town refuse incineration plant-wide electrical power plant equipment installation and commissioning works
|
2005 ~ 2006
|
|
10
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Shenzhen Pinghu Town garbage incineration power plant-wide factory-controlled instrument installation, commissioning works
|
2005 ~ 2006
|
|
11
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Shenzhen Pinghu Town garbage incineration power plant turbine generator group of machines and installation works
|
2005 ~ 2006
|
|
12
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Shenzhen Pinghu Town garbage incineration power plant turbine installation of the pipeline between technology
|
2005 ~ 2006
|
|
13
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Shenzhen Pinghu Town garbage incineration power plant closure of the entire plant fire
|
2005 ~ 2006
|
|
14
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Shenzhen Pinghu Town garbage incineration power plant-wide factory installation of the television industry
|
2005 ~ 2006
|
|
15
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Shenzhen Pinghu Town garbage incineration power plant boiler flue gas between the body and Lighting Project
|
2005 ~ 2006
|
|
16
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Zhongshan City Centre delegation garbage incineration power plant-wide factory-controlled instrument installation, commissioning works
|
2005 ~ 2006
|
|
17
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Zhongshan City Centre delegation garbage incineration power plant turbine generator group of machines and installation works
|
2005 ~ 2006
|
|
18
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Zhongshan City Centre delegation garbage incineration power plant smoke the whole plant, the production installation of the wind
|
2005 ~ 2006
|
|
19
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Zhongshan City Centre delegation garbage incineration power plant circulating pump room equipment and technology pipeline installation works
|
2005 ~ 2006
|
|
20
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Zhongshan City Centre delegation garbage incineration power plant air compressor equipment and the installation of the pipeline process
|
2005 ~ 2006
|
|
21
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Zhongshan City Centre delegation garbage incineration power plant and process water pumping station equipment installation of the pipeline
|
2005 ~ 2006
|
|
22
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Zhongshan City Centre delegation garbage incineration power plant high water the whole plant and the installation of water pipeline
|
2005 ~ 2006
|
|
23
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Zhongshan City Centre delegation garbage incineration power plant-wide factory installation of the television industry
|
2005 ~ 2006
|
|
24
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Zhongshan city centre groups 40 tons of garbage incineration power plant installation of the steel structure joint platform
|
2005 ~ 2006
|
|
25
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Longgang District, Shenzhen City garbage incineration power plant-wide overhaul of electrical equipment factory
|
2006 ~ 2007
|
|
26
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Longgang District, Shenzhen City garbage incineration power plant-wide factory-controlled instrument maintenance works
|
2006 ~ 2007
|
|
27
|
Shenzhen City Jian'an (Group) Co., Ltd.
|
Longgang District, Shenzhen City garbage incineration power plant Turbine and ancillary equipment maintenance works
|
2006 ~ 2007
|
| 28 |
China petrochemistry group tenth construction company |
The Quanzhou spring port area Fujian refinery ethylene installment decomposition cold sector 503 unit process tube the installation work |
2008 |
| 29 |
In the fontanel burns the city fuel gas development limited company |
The Tianmen CNG air entrainment station process unit the installation work |
2008 |
| 30 |
In Ningxia depth natural gas development limited company |
The center half back city CNG air entrainment station process unit/electricity the installation work |
2008 |
| 31 |
The Baotou Shanghai silver natural gas fills with gas the limited company |
The Baotou Dulan plot CNG automobile air entrainment station process unit/electricity the installation work |
2008 ~2009 |